Kathmandu Valley Road Repair Has Been Almost Finished



KATHMANDU: Repair works of streets in the Kathmandu Valley have been practically finished. The street upkeep began from mid April in the midst of the across the country lockdown.

Out of the objective of fixing 41 kilometers in the financial year of 2019/20, overlaying of in excess of 40 kilometers has been done, the division street office said including that fix of outstanding parts would be finished soon.

Street support has been put on top need, said the division office boss Kuber Nepali. Blacktopping of the vast majority of the streets along Gaushala-Chabahil has likewise been finished.

Wellbeing security cautions have been kept up in the midst of the episode of pandemic while undertaking all these development and fix works, he said.

The development of streets and extensions anyway has neglected to accomplish the objective. Of the objective of developing 30 kilometers streets inside the FY 2019/20, the development of just 12 kilometers has been cultivated up until this point, he said.

Absence of workforce and development materials has aggravated the issue, he further noted. Blacktopping of the street in Sitapaila territory is in progress. Moreover, development of streets along Gaushala-Chabahil and Putalisadak is likewise progressing.

The development is being embraced by the street division office in close coordination with the Kathmandu Upatyaka Khanepani Limited.